4 weeks to go... PANIC STATIONS

Okay here's where i'm at. The plan is to finish cleaning scene 1 over le weekend, scan it on Monday. Also finish in-betweening scene 3 part5 over the weekend (cleaning it simultaneously) and scan on Monday.  Block scene 4 THE DREADED LINKY SCENE over weekend, test on Monday.

MONDAY 8TH:

  • SCAN scene 1 and scene 3 (part 5), TRACK both (try and find slaves to scan)
  • TEST scene 4 blocks and amend
  • finish amending/ cleaning scene 6 and TEST
TUESDAY 9TH:
  • SCAN scene 6 and TRACK
  • CLEAN keys for scene 4
WEDNESDAY 10TH:
  • INBETWEEN scene 4 
  • DOJ-CON meeting
THURSDAY 11TH:
  • TEST scene 4 and SCAN (unless amendments needed)
  • CLEAN scene 2
  • LIFE DRAWING meeting
FRIDAY 12TH:
  • DOJ-CON PHOTO OP
  • Match up DRESS KEYS for scene 2, CLEAN
  • INBETWEEN dress layer scene 2
SATURDAY 13TH:
  • FUNDRAISER: DOJ-CON ALL DAY